Planner premium kept the scheduling half of Project Online: Gantt timelines, dependencies, critical path, a single baseline, and portfolios of premium plans. It did not keep the enterprise half: there’s no shared resource pool, no timesheets, no Project Web App, and no automatic migration path. Project Online retired on September 30, 2026, and Microsoft sends those enterprise features to two other products (Microsoft Community Hub). If your PMO ran on resource management and timesheets, Planner premium is the wrong place to land. If you used Project Online to schedule projects, premium covers most of what you used.
What does Microsoft say replaces Project Online?
There are three destinations, and each gets a different part of Project Online. Microsoft’s retirement post (published September 5, 2025, updated August 24, 2026) sets September 30, 2026 as the retirement date. It says Planner premium features “deliver portfolios, baselines, dependencies, and Gantt charts.” It places “resource management tools” in Project Server Subscription Edition, and “timesheet management and resource scheduling” in Dynamics 365 Project Operations (Microsoft Community Hub).
So Microsoft itself doesn’t describe Planner premium as a one-to-one replacement. It’s the destination for scheduling. Resource management and timesheets go elsewhere.
Side by side: what moved and what didn’t
| Capability | Project Online | Planner premium (Plan 3 / Plan 5) |
|---|---|---|
| Gantt timeline, dependencies, milestones, critical path | Yes | Yes (Microsoft Support) |
| Baselines | Yes | One baseline per plan; to update it you delete and recapture (Community Hub, Jan 2025) |
| Portfolios | Project Center across PWA projects | Premium plans only; basic plans and Project Online projects aren’t supported (Microsoft Support) |
| Enterprise resource pool, capacity across projects | Yes | No (Microsoft Q&A) |
| Per-plan resource views | Resource usage | People view and Capacity view, both inside one plan (MC1474110) |
| Timesheets | Yes | No (Microsoft Learn FAQ) |
| Project Web App site | Yes | No; data lives in Dataverse |
| Reporting | OData feed + Power BI content pack | Dataverse connector + a template you set up yourself; local custom fields “aren’t available for reporting” (Microsoft Learn FAQ) |
| Migration from Project Online | — | No automatic path (Microsoft Q&A) |
Reporting is the row with the most to rebuild, and it has its own page: Planner premium reporting after Project Online.
What carried over well?
The scheduling engine. Microsoft’s comparison page lists the premium-only features: Timeline (Gantt), task dependencies, milestones and custom fields, critical path, backlogs and sprints, goals, custom calendars and task history (Microsoft Support). A Microsoft moderator answering a Project Online migration question in April 2026 confirmed that premium supports “Timeline (Gantt), dependencies, milestones, critical path, custom fields, and premium scheduling views, but it is simpler and less customizable compared to Project Online” (Microsoft Q&A).
A project manager who opened Project Online to build and track one schedule at a time will recognize most of premium.
What moved over in a weaker form?
Baselines. Premium has them on Plan 3 and Plan 5, with start, finish, effort and duration variance at plan level. Microsoft’s January 2025 update still says “You can capture only one Baseline at the moment,” and you update it by deleting and recapturing (Microsoft Community Hub). Governance is also thin. A July 2026 feature request asks that “baseline creation, replacement, and deletion should not remain freely available to every user who can edit the plan” (Microsoft Community Hub). It had no replies when checked on November 25, 2026.
Portfolios. A portfolio collects premium plans and shows each plan’s manager, percent complete, dates and a manual status, with a roadmap of one row per plan. Per Microsoft’s support page, “basic plans aren’t currently supported,” and neither are Project Online projects (Microsoft Support). Most organizations run both plan types, which is a separate problem covered in Planner portfolios with basic and premium plans.
What didn’t move at all?
The enterprise resource pool. This is the loss teams mention most. Asked what Plan 5 adds for enterprise resource management, a Microsoft MVP answered that it “is only available in the Project Online application. It is not available in Project for the Web (aka Planner Premium)” (Microsoft Q&A). On a Community Hub thread about the same question, one poster relayed a Microsoft support call: “the resource allocation management is ONLY available in project online…NOT the new planner or premium planner” (Microsoft Community Hub). The capacity heat maps and resource engagements on Microsoft’s own resource management page are Microsoft Project features, not Planner premium ones.
Premium does have resource views now, but they work inside a single plan. The People view is premium-only. Message Center post MC1474110 (published September 18, 2026, last updated October 15, 2026) rolled out a Capacity view for Planner Plan 3 users, with general availability running late October to early November 2026. Microsoft describes it as “a timeline of who is working on what” that “appears as a new view on existing plans” (MC1474110). The post doesn’t say it rolls up across plans. The July 2026 feature request quoted above asks for exactly that: “a consolidated capacity management capability across all plans, programs, and portfolios” (Microsoft Community Hub). The per-plan views in detail are on the Planner capacity view page.
Timesheets. Microsoft’s Project for the web FAQ answers “Does Project for the web include a way to record timesheets?” with “No” (Microsoft Learn). Premium plans are Project for the web plans under a new name.
PWA and a migration path. The same April 2026 moderator answer: “there is no native and automatic path to migrate from PWA to Planner Premium,” because Planner uses Dataverse while PWA uses SharePoint/Project Online. On a .mpp import, “some data like resources and baselines are not imported so you may need to reassign” (Microsoft Q&A).
So which one fits your team?
| If Project Online was mostly… | Go to |
|---|---|
| Scheduling individual projects: Gantt, dependencies, critical path | Planner premium. It covers this. |
| A PMO portfolio of scheduled projects with a status per project | Planner premium portfolios, if all the plans are premium |
| An enterprise resource pool, capacity across projects, resource requests | Project Server Subscription Edition (on-premises), per Microsoft’s retirement post |
| Timesheets and resource scheduling tied to cost | Dynamics 365 Project Operations, per the same post |
The trap is moving a resource-managed PMO into Planner premium because it’s the cheapest licence, then finding the resource pool missing. Premium answers “is this project on schedule.” Project Online could also answer “who has room across all our projects,” and premium doesn’t.
Where Team Workload fits, and where it doesn’t
Team Workload answers a smaller question than a resource pool: what each person is holding across every plan, both basic and premium. It reads premium plans from Dataverse after a one-time Connect step and shows them next to basic plans, grouped by person, with due dates and overdue tasks.
To be exact about the limits, it counts tasks and assignments. It doesn’t plan hours against availability, keep a resource pool, level assignments, or record timesheets. It is not a Project Online replacement. If your team lives in Planner and the question you lost is “who is buried across all these plans,” it answers that on one screen, with a 30-day free trial.